2021-22 Resheeting Program Update

Published on 25 March 2022

TimePhoto_20220217_092916.jpg

Many of Mansfield Shire’s unsealed, gravel roads have been resheeted, with more scheduled to be completed over coming months.

The program includes the excavation and installation of numerous culverts, shoulder and table drain reshaping to improve drainage and the resheeting itself, which involves the installation of 100mm of crushed rock on identified priority sections of the roads to enhance and strengthen the road condition.

Mayor Cr Tehan said the program provided critical links for agriculture business, residents and visitors.

“This is a significant program with more than $2.2 million spent on the re-sheeting program. Alpine Civil have been ploughing through the work and we’re pleased to see safer, more efficient roads shaping up around the Shire.”

The following gravel roads have had works completed:

  • Gonzaga Lane, Merrijig
  • McLeod Lane, Mansfield
  • Long Lane West, Mansfield
  • Olivers Road, Mansfield
  • Banumums Road, Mansfield
  • Knights Road, Merton
  • Howes Creek Road, Mansfield
  • Pollards Road, Mansfield
  • Coles Road, Woodfield (in progress, drainage yet to be completed)
  • Rifle Butts Road, Mansfield
  • The Sideling, Jamieson

In coming months, the following roads will have works completed, including:

  • Old Tonga Road, Mansfield
  • Lake Nillahcootie Road to Youngs Road, Barjarg
  • Sandy Creek, Barjarg
  • Tabletop Road, Tolmie
  • Walkers Road, Bridge Creek
  • Blue Range, Bridge Creek
  • Saligari Road, Barwite
  • Woolshed Road, Woodfield
  • Shorts Road, Merton
  • Old Strathbogie Road, Merton
  • Kiernans Road, Bonnie Doon
  • Glen Creek Road, Bonnie Doon
  • James St, Bonnie Doon

Council is responsible for a road network of 580 kilometres of unsealed roads as a part of a total road network of 840 kilometres.